Tesla

Megapack 2 XL 2-Hour C010 / C011

Grid-ScaleAC Block

Updated Sep 28, 2026

Grid-ScaleAC BlockUpdated Sep 28, 2026

3.854 MWh nominal energy defines Tesla Megapack 2 XL 2-Hour C010 / C011, supplied as an AC block. It has about a 2-hour duration and reaches 91.7% AC round-trip efficiency. It weighs 38.1 tonnes (83,996 lb).

Use Cases

Tesla Megapack 2 XL 2-Hour C010 / C011 has energy capacity in the utility-scale class. Its supported protocols include DNP3, used in utility control systems, and together point to use in front of the meter, directly on the electricity network.

Capabilities

Tesla Megapack 2 XL 2-Hour C010 / C011 has a shortest listed configuration of 2 h, which points to capacity value, being counted on as supply when the network is tight. Its AC block includes the inverter, and the specifications suggest renewable colocation, sitting next to a wind or solar plant and sharing its grid connection. That 2 h configuration makes Tesla Megapack 2 XL 2-Hour C010 / C011 a candidate for peak shaving, reducing the peak load at the connection point. The same configuration indicates grid services, support that helps operators run the electricity network.

Nominal energy

3.85MWh

Rated AC power

1.93MW

Duration

2flexible

Round-trip efficiency (AC)

91.7 %AC

What does this system typically cost?

BESSBASE.com user price estimates for Megapack 2 XL 2-Hour C010 / C011 by Tesla and similar storage systems. The ranges are LDP (Landed Duty Paid) prices per kWh that cover all expenses of delivering the goods to the buyer's premises, including production, shipping, sales margins, and import duties.

Sign up to see and submit price estimates.

BESSBASE.com users can privately compare and submit prices for Megapack 2 XL 2-Hour C010 / C011 by Tesla and similar systems across 20+ international markets.

Energy & Power

Nominal energy
3.85MWh
Rated AC power
1.93MW
Duration
2 hourflexible
Round-trip efficiency (AC)
91.7 %

Architecture

Installation
Indoor or outdoor

DC Side

AC Side

AC voltage
480 V
AC voltage parameters
3-phase
Grid frequency
50 Hz / 60 Hz

Physical & Footprint

Dimensions (W × D × H)
8,800 × 1,650 × 2,785mm
Weight
38.1t

Battery Cells

Cell supplier
LG Energy Solution

Lifespan

Protection

Enclosure protection
IP66NEMA 3RIP20

Full Specification Sheet

Members

The rest of this spec sheet is for members

3 more specification blocks on this product. Create a free account to see every field on every product.

You stay on this page — it fills in as soon as you are signed in.

Plant Round-Trip Efficiency

Duration
duration 2 h
0.5C
—
State of health
new system
as-new
—
AC block (battery + PCS)
rte_ac 91.7 % @2 h
round trip @ 2 h
91.7 %
PCS (DC/AC)
Not Applicable for AC Block ESS
each way
—
—
Transformer LV/MV
typical default
each way
98.01 %
Transformer MV/HV
typical default
each way
98.01 %
Cables (all segments)
typical default
each way
98.8 %
Auxiliary power (plant's own consumption)
typical default
−4.4 pts
Plant Round-Trip Efficiency at the Point of Interconnection
82.7 %
40 %100 %
1.209MWh charged for every 1 MWh discharged
Both measured at the grid connection point. The plant's own power use is already included in the losses.

The calculator estimates the full "plant" round-trip efficiency (RTE) at the point of interconnection. Some values are pre-blocked depending on information on a particular ESS. The rows that are marked "each way" are one-way efficiencies; they are applied on charge and again on discharge. We then square them. To enter a bundled PCS efficiency value, use its rated-power value, not peak. If the PCS skid already includes the LV/MV transformer, set Transformer LV/MV to 100 % so those losses are not counted twice.

Site Space Required

single unit clearance 3 m / side
113.2m² total site area · 1 × 1
1,219 ft²0.0113 ha0.028 acres29.4 m² / MWh317 ft² / MWh
Unit W × D
8.8 × 1.65 m
28.87 × 5.41 ft
Site envelope
14.8 × 7.65 m
48.56 × 25.1 ft
Per unit
113.2 m²
Installed energy
3.85 MWh
1 × nameplate
Units1
Per row1
Clearance between unitsShared

Shared: one 3 m aisle serves both neighbours. Dedicated: each unit keeps its own 3 m, so gaps double to 6 m.

Clearance allowance
6m per axis · 3 m per side
19.69 ft per axis · 9.84 ft per side

Single unit — matches the stored area_sqm convention.

More Tesla Systems

8
CompareLogoVendorSystemEnergyPowerDurationBattery CellOpen
Tesla
Megapack 3DC Block
5MWh2.5MWAC1–8hflexLFP
Tesla4.3MWh1.08MWAC4h0.25C · flex—
Tesla4.3MWh1.9MWAC2–4hflexLFP
Tesla3.92MWh0.98MWAC4h0.25C · flex—
Tesla
Megapack 2 XL 2-Hour C010 / C011AC Block · cabinet
3.85MWh1.93MWAC2hflex—
Tesla3.09MWh0.77MWAC4hLFP
Tesla2.92MWh1.46MWAC2hLFP
Tesla
Megapack 2 (2-Hour)AC Block · cabinet
2.6MWh1.3MWAC2–4hflex—

About the Vendor

TeslaTier-1Listed Company

Founded in 2003 and based in Austin, Texas, Tesla expanded from electric vehicles into battery energy storage with Megapack and Powerwall. It deployed 31.4 GWh in 2024 and 43.5 GWh in the 12 months through the third quarter of 2025, including a record 12.5 GWh in one quarter, which shows its BESS manufacturing scale for utility and project finance counterparties.

Production scale20+ GWh
Company sizeMajor (10000+)
Vertical integrationHighest
BankabilityOverall Positive

How to Read the Product Page

This profile of Megapack 2 XL 2-Hour C010 / C011 by Tesla is assembled exclusively from public data to support early-stage screening and requires additional due diligence.

Always confirm these terms and technical specifications directly with the vendor and project stakeholders. Reflect all agreed-upon details in the legal agreements before making any investment decisions.

BESSBASE.COM

Your trusted database of battery energy storage systems

© 2026 BESSBASE.com. All rights reserved.