INTILION scalepac8 is an LFP battery energy storage system with 2.032 MWh nominal energy and about a 2-hour duration. It is supplied as an AC block with air or liquid cooling and delivers 90% AC round-trip efficiency. The system uses 306 Ah prismatic cells and weighs 22.4 tonnes (49,383 lb).
Use Cases
The specifications of INTILION scalepac8 together point to use in front of the meter. Its energy capacity is within the utility-scale range. It is certified to medium- or high-voltage grid connection rules (VDE-AR-N 4110).
Capabilities
For INTILION scalepac8, the specifications suggest renewable colocation, operating alongside a wind or solar plant on one site, and its AC block includes the inverter. Its shortest listed configuration is 2 h. That configuration makes INTILION scalepac8 a candidate for peak shaving, cutting the power drawn from the grid at peak times; indicates grid services, support for the operation of the electricity network; and the specifications suggest capacity value, counting as firm supply toward a network's peak needs.
Nominal energy
2.03MWh
Duration
2hour
C / P rate
0.5P
Round-trip efficiency (AC)
90 %AC
What does this system typically cost?
BESSBASE.com user price estimates for scalepac8 by INTILION and similar storage systems. The ranges are LDP (Landed Duty Paid) prices per kWh that cover all expenses of delivering the goods to the buyer's premises, including production, shipping, sales margins, and import duties.
Sign up to see and submit price estimates.
BESSBASE.com users can privately compare and submit prices for scalepac8 by INTILION and similar systems across 20+ international markets.
Energy & Power
Architecture
DC Side
AC Side
Physical & Footprint
Battery Cells
Lifespan
Protection
Full Specification Sheet
MembersThe rest of this spec sheet is for members
3 more specification blocks on this product. Create a free account to see every field on every product.
You stay on this page — it fills in as soon as you are signed in.
Plant Round-Trip Efficiency
The calculator estimates the full "plant" round-trip efficiency (RTE) at the point of interconnection. Some values are pre-blocked depending on information on a particular ESS. The rows that are marked "each way" are one-way efficiencies; they are applied on charge and again on discharge. We then square them. To enter a bundled PCS efficiency value, use its rated-power value, not peak. If the PCS skid already includes the LV/MV transformer, set Transformer LV/MV to 100 % so those losses are not counted twice.
Site Space Required
Shared: one 3 m aisle serves both neighbours. Dedicated: each unit keeps its own 3 m, so gaps double to 6 m.
Single unit — matches the stored area_sqm convention.
More INTILION Systems
8| Compare | Logo | Vendor | System | Energy | Power | Duration | Battery Cell | Open |
|---|---|---|---|---|---|---|---|---|
| INTILION | INTILION | scalecube 4073-05CDC Block · 20 ft container | 4.07MWh | — | —0.5C | LFP306 Ah · Prismatic | |||
| INTILION | scalepac8AC Block · cabinet | 2.03MWh | — | 2h0.5C | LFP306 Ah · Prismatic | |||
| INTILION | scalepac7AC Block · cabinet | 1.78MWh | — | 2h0.5C | LFP306 Ah · Prismatic | |||
| INTILION | scalepac6AC Block · cabinet | 1.52MWh | — | 2h0.5C | LFP306 Ah · Prismatic | |||
| INTILION | scalepac5AC Block · cabinet | 1.27MWh | — | 2h0.5C | LFP306 Ah · Prismatic | |||
| INTILION | scalepac4AC Block · cabinet | 1.02MWh | — | 2h0.5C | LFP306 Ah · Prismatic | |||
| INTILION | INTILION | scalecube 407-05CDC Block · cabinet | 0.41MWh | — | —0.5C | LFP306 Ah · Prismatic | |||
| INTILION | scalepacAC Block · cabinet | 0.25MWh | 125MWAC | —0.5C | LFP306 Ah · Prismatic |
About the Vendor
Founded in 2019 as a spin-off from the HOPPECKE Group, INTILION put the group’s lithium-ion work into one company focused on stationary energy storage. Based in Paderborn, Germany, it supplies modular lithium-ion systems from 1 to about 100 MWh and works as an energy storage provider in the DACH region.
How to Read the Product Page
This profile of scalepac8 by INTILION is assembled exclusively from public data to support early-stage screening and requires additional due diligence.
Always confirm these terms and technical specifications directly with the vendor and project stakeholders. Reflect all agreed-upon details in the legal agreements before making any investment decisions.